Morocco's Noor Midelt I Solar Project Set to Begin Construction in January 2027

Ali Sharawy
novembro 24, 2026
•
5 Min

Morocco's Noor Midelt I solar project is expected to begin construction on 15 January 2027, following nearly seven years of delays and changes to its technical design. The project will combine 632.853 MWp of solar photovoltaic capacity with a battery energy storage system of 1,323.96 MWh, with completion targeted for July 2028.

Construction scheduled for January 2027

Construction works are scheduled to begin on 15 January 2027 and continue for 18 months, with completion expected on 15 July 2028.

The latest timeline was disclosed by China Energy International Group through a tender published on 18 November for the procurement of air-insulated switchgear (AIS) equipment. The tender was published on China's Yifangbao platform, with submissions open until 21 November.

The procurement process follows another tender issued on 12 November for the project's main power transformers, indicating progress in preparations for construction.

Updated design combines solar PV and battery storage

Under its revised technical configuration, Noor Midelt I will combine large-scale solar photovoltaic generation with a battery energy storage system (BESS).

The project will have an installed solar PV capacity of 632.853 MWp, supported by battery storage with a capacity of 1,323.96 MWh.

The revised configuration replaces the original design, which combined photovoltaic generation with concentrated solar power (CSP). The move towards a PV and battery-based system changes how the project will generate and store electricity.

A project delayed by technical and contractual changes

The development process began in 2019, when the project was initially awarded to a consortium led by EDF Renewables. The original design combined solar PV with concentrated solar power technology.

However, disagreements related to the CSP component delayed implementation and led to a reassessment of the project's technical configuration.

The revised design replaced the original hybrid approach with a system based on solar PV panels and battery energy storage.

Chinese-led consortium takes over project development

Following the redesign, a Chinese consortium took the lead in advancing the project. The construction contract was signed on 27 August, with China Energy International Group announcing the agreement in September.

The subsequent procurement tenders for transformers and AIS equipment mark further steps towards the planned construction start in January 2027.

Battery Storage Takes a Central Role in Morocco's Solar Expansion

The renewed progress on Noor Midelt I marks an important step for one of Morocco's long-delayed solar developments.

Its revised configuration combines substantial solar generation capacity with large-scale battery storage, allowing electricity to be stored and made available beyond periods of solar generation.

The project also reflects the growing role of energy storage in Morocco's renewable energy strategy. As the country expands its solar and wind capacity, storage infrastructure will become increasingly important in managing variable renewable generation and supporting electricity supply.

If the latest construction schedule is maintained, Noor Midelt I will move from years of delays into implementation, adding another major solar and storage development to Morocco's energy infrastructure.